Fire Station #3 Construction Update

Progress is being made on the construction of Fire Station #3, located just north east of the intersection of Lower Seguin Road and Hollering Vine. The station will be a 12,000 square foot facility equipped with an apparatus bay for fire trucks; living quarters; and facilities such as offices, a workout room, and a large community room intended to be used for community meetings.

Construction update - week of June 12, 2019

  • The roof is 90%complete on the bay side.
  • The steel roof decking is about 100% complete on the living quarters side.
  • Water proofing is complete on the bay side CMU walls
  • Water and sewer lines are complete to the site.
  • Metal stud walls are being installed.
  • Overhead mechanical & electric is being installed
  • Exterior tile is starting to be installed on the bay side  

Designed by BRW Architects and constructed by T.S. Byrne Construction Inc.

Project Costs: $8 million

Fire Station #3 is on track to open by Fall 2019. Render 2-1