Fire Station #3 Construction Update

Progress is being made on the construction of Fire Station #3, located just north east of the intersection of Lower Seguin Road and Hollering Vine. The station will be a 12,000 square foot facility equipped with an apparatus bay for fire trucks; living quarters; and facilities such as offices, a workout room, and a large community room intended to be used for community meetings.

Construction update - week of September 09, 2019

  • Site concrete is 90% complete
  • Schertz Parks Dept will be planting trees on the site this week
  • Irrigation system has been installed 
  • The roof is dried in on the Station
  • The drop-in ceiling has started to be installed
  • Bay doors have been installed on the front of station
  • Retaining Wall in front of Station is complete
  • Windows are complete 
  • Sheetrock walls are complete 
  • Stone veneer is complete on the outside of the Station
  • Water and sewer lines are complete to the site.
  • Overhead mechanical is about 95% complete
  • Exterior tile is 60% installed  
  • Plumbing on the interior of the building has started to be installed 

Designed by BRW Architects and constructed by T.S. Byrne Construction Inc.

Project Costs: $8 million

Fire Station #3 is on track to open by Fall 2019. Render 2-1