Fire Station #3 Construction Update

Progress is being made on the construction of Fire Station #3, located just north east of the intersection of Lower Seguin Road and Hollering Vine. The station will be a 12,000 square foot facility equipped with an apparatus bay for fire trucks; living quarters; and facilities such as offices, a workout room, and a large community room intended to be used for community meetings.

Construction update - week of May 20, 2019

  • The steel roof decking is complete on the bay side.
  • The steel roof decking is about 50% complete on the living quarters side.
  • Structural steel beams are 100% complete.
  • Water proofing has started on the CMU walls on the bay side.
  • Water and sewer lines are 90% complete to the site.
  • Roofing will start this week on the bay side 

Designed by BRW Architects and constructed by T.S. Byrne Construction Inc.

Project Costs: $8 million

Fire Station #3 is on track to open by Fall 2019. Render 2-1