SPAM Rehabilitation Projects

On February 11, City Council awarded a construction contract to Alamo City Constructors, Inc. for the 2018 SPAM Rehabilitation Projects.

This project consists of three different project areas. Randolph between Main and Exchange will be reconstructed; Schertz Parkway between Live Oak and Beck will receive a “mill and overlay”; and a portion of the Northcliffe area will have their streets rehabilitated.

The Randolph reconstruction will replace the existing pavement with a new, stronger asphalt pavement section. The new section will be able to support the traffic loads, unlike the current pavement section. This section of Randolph will be completely closed during the reconstruction process. Traffic will be detoured around the project area. 

The Schertz Parkway “mill and overlay” involves grinding off the existing pavement surface. After the surface is removed, new layers of asphalt will be placed. In order to increase the strength of the pavement section, so it can better withstand the traffic loads, the entire existing asphalt and a small portion of the base underneath the pavement will be removed. This is so we can replace the existing two inches of asphalt with four inches of new asphalt. The new asphalt pavement will be placed in two layers. There will be alternating lane closures in the project area during the construction process. Two-way traffic and business access will be maintained, but it may take longer to get through the project area during construction. Please be patient and allow extra time while going through the project area.

The Northcliffe portion of the project involves making some sidewalk and curb and gutter repairs in the project area. Not all of the sidewalk and curb and gutter will be replaced as the main focus of this project is to address the streets. After the concrete repairs are completed, the existing pavement and base material underneath will be ground up and blended together. This mixture will next be cement stabilized and re-shaped. A new layer of asphalt will be placed on top of the blended and stabilized material. This new pavement structure will be stronger and more durable than the existing pavement. During construction, there will be times the street may resemble a gravel road and parking along the street will not be allowed. Please be patient as this needed project is completed

The contractor started work on this project on April 6. The contractor started two project areas at the same time. They started the concrete repairs in the Northcliffe area and the Randolph reconstruction first.

Construction Start: April 2020
Construction Final Completion: August 2020
Awarded Construction Contract: $2,881,784.00
Final Construction Contract:
Funding Source: Proceeds of 2016 and 2017 Certificates of Obligation for Road Improvements

Project Updates

  1. September 1, 2020
  2. June 12, 2020
  3. June 3, 2020
  4. May 15, 2020
  5. May 8, 2020
  6. May 1, 2020
  7. April 24, 2020
  8. April 17, 2020
  9. April 9, 2020
All of the work on the project is complete. We hope you enjoy the new streets!

Project Areas

  1. John Nowak, P.E.

    Engineer
    Phone: 210-619-1825