FM 1103 Utility Relocations

Before TxDOT can release the FM 1103 expansion project for construction, the City of Schertz must relocate the existing water and wastewater lines that are in conflict with the planned roadway and drainage improvements. The utility relocation project was awarded to D. Guerra Construction on April 9th and the Notice to Proceed was issued on July 29th.  Construction began in August.

Construction Start: August 2019
Construction Completion: February 2020
Cost of Construction: $900,000.00
Funding Source: CO 2018 Bond

UPDATE -  December 2019

  • Installation of approximately 600 feet of waterline was installed near the intersection of IH-35 and FM 1103.
  • The waterline crossing FM 1103 near IH-35 was installed. 
  • In total, approximately 2,000 feet of waterline has been installed.
  1. Scott McClelland, E.I.T.

    Project Manager
    Phone: 210-619-1822

FM 1103 Utility Relocations Location Map

Progress Photos

20191216_110720
20191209_104343
20191209_104413
20191212_145743